Monday, October 15, 2012

Yet another Bypass construction update

Chris forwarded the following information to me that he received from the CIB traffic committee:


ROAD UPDATES

  1. The  revised current schedule is to put traffic on the new northbound Bypass lanes from 10th St. to 17th St.on October 16. Traffic will still be restricted to one lane each direction, as they still need to construct center curb in that area. 
  2. The traffic signal at 17th Street and the Bypass is also scheduled to be activated on October 16.
  3. College Mall Road between 2ndand 3rd Street will close on or afterMonday, Oct. 22 for replacement of a 48-inch storm sewer line. Weather permitting, traffic will be detoured for about a week’s time over 2nd Street, Woodcrest Drive and 3rd Street.
Please note especially item 3 above. As far as I can tell, the project is still on track to be open for traffic by the end of November, although the final layer of asphalt may need to be done next spring, much like the north part of the project last winter.